Development or a new land use authorized through a planning permit granted in compliance with this Zoning Code shall be established only as approved by the review authority, and in compliance with any conditions of approval, except where a change to the project is approved as follows:
A.
Application. An applicant shall request a desired change in writing, and shall also furnish appropriate supporting materials and an explanation of the reasons for the request. A change may be requested either before or after construction, or establishment and operation of the approved land use.
B.
Changes approved by Director. The Director may authorize one or more changes to an approved site plan, architecture, conditions of approval, or the nature of the approved land use where the Director first determines the change is minor, and finds that each change:
1.
Is consistent with all applicable provisions of this Zoning Code;
2.
Does not involve a feature of the project that was a basis for findings in a negative declaration or environmental impact report for the project; and
3.
Does not involve a feature of the project that was specifically addressed or was a basis for conditions of approval for the project or that was a specific consideration by the review authority (e.g., the Director, Commission, or Council) in the project approval.
The Director may choose to refer any requested change to the original review authority for review and final action.
C.
Changes approved by original review authority. A proposed change that does not comply with the criteria in Subsection B above, shall only be approved by the original review authority for the project through a new permit application processed in compliance with this Zoning Code.