§ 18-367. Request for inspection.  


Latest version.
  • (a)

    Requests for inspection of any site subject to this article shall be made to the director at the following phases of activity; such a request shall be made at least two full business days in advance of the desired day of inspection:

    (1)

    When the site has been cleared of vegetation and unapproved fill; and scarified, benched, or otherwise prepared and before any fill is placed; and the erosion control and sediment control measures to be implemented in this phase have been placed.

    (2)

    When approximate final elevations have been established; drainage terraces, swales and other drainage devices have been graded and are ready for paving; berms have been installed at the top of slopes; and the erosion control and sediment control measures to be implemented in this phase have been placed.

    (3)

    When work has been completed; slope planting established and irrigation systems installed, if required; and the erosion control and sediment control measures to be implemented in this phase have been placed.

    (b)

    The director, upon inspection of the site, shall notify the permittee:

    (1)

    That the phase of work inspected is approved; or

    (2)

    What deficiency, correction or other work needs to be completed before approval of that phase.

(Ord. No. 99-11, § 3(16A.52.270), 6-16-1999)