§ 66-181. Installment payments for retiring the deferred fee.  


Latest version.
  • After complying with Section 16.87.084 [66-180], subsequent installment payments shall be made to the Department as follows: A fee installment of 20% of the total roadway and transit fee obligations calculated for the shell building shall be due and payable to the county every 12 months subsequent to the issuance of the shell building permit until the total deferred fee has been retired. The county will mail a billing notice to the property owner for each installment fee payment no later than 30 days prior to the date upon which the payment is due. The final installment payment to retire the deferred fee shall be due and payable to the county 48 months after the issuance of the shell building permit. After receipt of the final fee installment, the county shall record a notice for the affected property indicating that the debt for the deferred fee obligation has been retired.

(Ord. No. 97-01, § 2(16.87.086), 1-2-1997; Ord. No. 97-13, § 2, 3-26-1997; Ord. No. 97-17, § 2, 9-24-1997)