§ 66-181. Installment payments for retiring the deferred fee.
Latest version.
After complying with Section 16.87.084 [66-180], subsequent installment payments shall
be made to the Department as follows: A fee installment of 20% of the total roadway
and transit fee obligations calculated for the shell building shall be due and payable
to the county every 12 months subsequent to the issuance of the shell building permit
until the total deferred fee has been retired. The county will mail a billing notice
to the property owner for each installment fee payment no later than 30 days prior
to the date upon which the payment is due. The final installment payment to retire
the deferred fee shall be due and payable to the county 48 months after the issuance
of the shell building permit. After receipt of the final fee installment, the county
shall record a notice for the affected property indicating that the debt for the deferred
fee obligation has been retired.